Welcome to the Beta site. Beta means that you’re looking at the first version of the new Marine Data Exchange.
We’ll be continually testing and improving the site, so please let us know how we’re doing by getting in touch here

2013, EGS Ltd, Lynn and Inner Dowsing Offshore Wind Farms, Post-Construction Survey

2013, EGS Ltd, Lynn and Inner Dowsing Offshore Wind Farms, Post-Construction Survey

Top Categories:

Geophysical

Description

EGS (International) Ltd was contracted to undertake the 2013 Post-Construction hydrographic and geophyscial survey (Multibeam and side scan sonar systems) of the Lynn and Inner Dowsing (L&ID) Wind Farms and export cable routes.  Additionally, an environmental survey was required for the 54 No Cable Zones. 
With respect to the Scope of Work, the total survey operations were carried out in three phases as below:
 Phase 1 – Scour, trial pit and cable survey- carried out between 3rd October 2013 and 7th November 2013
 Phase 2 – High-resolution MBES survey of 10 turbine foundations -  carried out between 7th and 8th November 2013.
 Phase 3 – Environmental survey of No Cable Zones (NCZ) - carried out between 8th and 14th November 2013.

 EGSi subcontracted Benthic Solutions Limited (BSL) to carry out the environmental survey operations.

Dataset

Download All

DWG Data

Report

Download All

Phase 3 Survey Report

Phase 1 and 2 Survey Report