2017, Bibby Hydromap, Walney Offshore Wind Farms, Asset Integrity Survey 3

2017, Bibby Hydromap, Walney Offshore Wind Farms, Asset Integrity Survey 3

Topic categories:

Geophysical

Last series update:

May 2021

MEDIN approved

Industry:

Wind

Collection date:

May 2017 - May 2017

Development:

Walney

Publication date:

May 2021

Round:

2

Organisation:

Bibby Hydromap

Phase:

Post-construction

Description

Bibby HydroMap were commissioned in May 2017 by DONG Energy to carry out surveys for the crossing and proximity agreement on the WOW0102 wind farm. The surveys were completed under Bibby HydroMap’s Terms and Conditions. The surveys were carried out between 11/05/17 and 19/05/17.
The main objectives were as follows:
-	Minimum 100% coverage
-	Soundin...