Welcome to the Beta site. Beta means that you’re looking at the first version of the new Marine Data Exchange.
We’ll be continually testing and improving the site, so please let us know how we’re doing by getting in touch here

2010, Fugro Alluvial Offshore Limited, West of Duddon Sands Offshore Wind Farm, Geotechnical Investigation (Contract Part C - Cable Route)

2010, Fugro Alluvial Offshore Limited, West of Duddon Sands Offshore Wind Farm, Geotechnical Investigation (Contract Part C - Cable Route)

Top Categories:

Geotechnical

Description

Fugro Alluvial Offshore Limited (FAOL) was contracted by Fugro Seacore Ltd on behalf of DONG
Energy Power (UK) Ltd to perform a geotechnical investigation for the proposed West of Duddon
Sands Offshore Windfarm.
The site investigation was performed to provide soils information that would assist in the
geotechnical investigation associated with the survey.
The purpose of this geotechnical site investigation is to provide high quality, fit for purpose,
geotechnical data in a timely and cost effective manner. The geotechnical investigation shall
provide sufficient and adequate information about soil strata, strength and deformation
parameters to perform a detailed design of the proposed cable route.
The investigation work was performed aboard the vessels “Fugro Commander” and the
“Willendeavour”
Between 26th June to 23rd July 2010, 51 Vibrocores, and 26 Piezocone Penetration Tests
(PCPT’s) were performed at 25 locations requested by the Client.