2012, Zone 9 Celtic Array, Zonal Appraisal and Planning (ZAP) Report

2012, Zone 9 Celtic Array, Zonal Appraisal and Planning (ZAP) Report

Topic categories:

Other

Last series update:

May 2021

MEDIN approved

Industry:

Wind

Collection date:

Jul 2012 - Jul 2012

Development:

Zone 9 - Celtic Array

Publication date:

May 2021

Round:

3

Organisation:

Zone 9 Celtic Array

Phase:

Pre-construction

Description

In order to better understand the issues developers faced in previous leasing rounds for offshore wind, , CERI (now Celtic Array) adopted a new zonal approach to offshore wind development, as advocated by The Crown Estate (2010). This approach, termed Zone Appraisal and Planning (ZAP), a two year process and is a voluntary basement with no legal re...