2015, Fugro Geoconsulting S.A.S., Hywind Offshore Wind Farm, Landfall Ground Investigations
Statoil Petroleum ASA is developing the Hywind Scotland Pilot Park wind farm, off Peterhead in Scotland. Horizontal Directional Drilling (HDD) technology is chosen for the export cable installation at the landing, in Peterhead. Fugro Survey AS (FSAS) was contracted by Hywind (Scotland) Ltd to perform the nearshore geophysical survey at the cable landing area. The purpose of the survey was to collect information regarding the subsurface rock, surficial deposits and depth of bedrock along the proposed HDD tunnel, from shoreline to about 400m toward sea, within 15 metres water depths. The seismic refraction survey was carried out using “Hercules” and “Argosy” vessels for 10-hours operations per day between 11th and 26th May 2015. As well as reports detailing the Geophysical Surveys, there is also a Data Integration report within this series, which contains an integration of geophysical and geotechnical data acquired at the HywindScotland Landfall site.
2013-2015, Statoil, Hywind Offshore Wind Farm, Environmental Statement
To support the Marine Licence application, Hywind (Scotland) Limited (HSL) is required to produce a statutory Environmental Statement (ES) under the Marine Works (Environmental Impact Assessment) Regulations 2007 in order to determine whether there is potential for the Project to have any adverse effects on the environment. The ES includes consideration of navigational issues via a Navigational Risk Assessment (NRA) as well as an evaluation of potential impacts on Natura 2000 sites through a Habitats Regulations Appraisal (HRA) assessment. Depending on the findings of the EIA there may also be a requirement for a European Protected Species (EPS) Licence and/or Wildlife Licence. Marine Scotland will confirm this requirement during the ES review. Throughout the EIA process the Design Envelope (previously known as Rochdale Envelope) approach has been used to assess the project design which could result in the greatest potential environmental impacts. Whilst this approach results in a conservative impact assessment; care must be taken to ensure the impacts predicted to arise from the project are not over estimated, such that they are unlikely to ever occur, and therefore undermine the EIA process. This series contains the complete Environmental Statement, including Non-Technical Summary.
2014, ORCA Marine, SULA Diving, Hywind Offshore Wind Farm, Marine Archaeological Assessment
ORCA Marine was commissioned by Xodus Group and Hywind (Scotland) Limited (HSL) to assess the potential impacts of the proposed marine wind turbine development of Hywind Scotland Pilot Park, approximately 25km east of Peterhead, Aberdeenshire, near Buchan Deep. This baseline assessment will identify any sites of archaeological or historical significance that might be affected by the proposed development and where / if appropriate make some initial suggestion for managing or mitigating any identified issues and impacts concerning the marine archaeological and heritage resource. The report incorporates a Desk Based Assessment (DBA) of the possible submerged cultural heritage within the Proposed Offshore Turbine Deployment Area and export cable route corridor prepared by Scientific Underwater Logistics and Diving (SULA Diving) on behalf of ORCA Marine. SULA Diving were also commissioned to assist in the evaluation of the remote sensing survey data (multi-beam echo sounder (MBES), side scan sonar (SSS), Magnetometer and sub-bottom Profiler (SBP)) obtained by survey company MMT on behalf of HSL. Also provided within this series is a document detailing key mitigation issues along the export cable route and offshore turbine deployment area, for discussion and agreement.
2014, Fugro GeoConsulting, Hywind Offshore Wind Farm, Geotechnical Investigations
The ST14460 geotechnical soil investigations provides information for anchoring of five floating wind turbines, and on the soil conditions along the export cable route from the wind farm area to Peterhead. The offshore activities were carried out from the DP II vessel 'Toisa Voyager' between 2014-03-28 and 2014-04-03. The operations were conducted on a continual 24-hour basis. At the planned Wind Farm site a total of 15 deep push seabed CPTUs were carried out to maximum possible penetration or planned target depth. Along the preliminary cable route a total of 19 shallow seabed CPTUs and 2 additional tests (re-runs) were performed. The onshore laboratory work was contracted out to the Danish Geotechnical Institute (GEO) and the Norwegian Geotechnical Institute (NGI). Tests on soil samples included grain size, plasticity, thermal conductivity and electrical resistivity.
Series2013, ORDTEK, Hywind Offshore Wind Farm, UXO Risk Assessment and Mitigation
Hywind Scotland (HWS) will be a pilot floating offshore wind project deploying up to 5 turbines that will be on a floating foundation anchored to the seabed. There may also be a requirement for a small amount of seabed infrastructure additional to the anchors. A single export cable from the project which will come ashore in Peterhead, Aberdeenshire. Statoil is the developer. The site is located in the area known as “Buchan Deep”, with a depth of water between approximately 93m – 120m. The HWS main site AOI is split by the Forties to Cruden Bay oil pipeline. Unexploded ordnance (UXO) residue from World War One (WWI), World War Two (WWII) and post-war dumping of explosive ordnance (EO) presents a potential risk to the development. Nevertheless, the UXO hazard can be managed safely and at best value to the project through a comprehensive understanding of the risks involved, the natural environment and the project development phases.
2013-2014, Metocean Services International, Hywind Offshore Wind Farm, Metocean Survey
Statoil have contracted Metocean Services International (MSI) to deploy a mooring for measurement of current profiles in 110m water depth offshore Scotland. Current measurements were undertaken with an upward-looking 300kHz ADCP and Aquadopp single point current meter, deployed near the seabed. The instrumentation was first deployed in early November 2013 and was demobilised in early November 2014. This report contains data collected during all three measurement periods in the measurement program, from 5 November 2013 to 4 November 2014.
Series2013, Xodus Group Ltd., Hywind Offshore Wind Farm, Hywind Pilot Park Project EIA Scoping Report
This Scoping Report, and accompanying navigational Preliminary Hazards Assessment (PHA) has been prepared in order to support the development of the Hywind Scotland Pilot Park and represents a formal request for a Scoping Opinion from Marine Scotland and Aberdeenshire Council, in consultation with the relevant statutory consultees. The request for a Scoping Opinion from Marine Scotland is for the Pilot Park and export cable and all offshore infrastructure below mean high water springs (MHWS) and the request for a Scoping Opinion from Aberdeenshire Council is for the export cable onshore and grid connection works (all works above mean low water springs, MLWS). The Scoping Report has been produced to facilitate the identification and initial assessment of the potential environmental impacts associated with the Project. It identifies the potential interactions there may be between the proposed Project and the environment in order to establish studies and/or surveys that might be required in order to better understand these interactions. Similarly, the aim of the PHA is to identify potential navigational hazards associated with the Project and determine, through consultation, how these hazards should be addressed as part of the NRA.
2013, Xodus Ltd., Hywind Offshore Wind Farm, Phase 1 Intertidal Survey
To support the development of the Hywind Scotland Pilot Park Project (‘the Project’), Statoil Wind Limited (SWL) is undertaking an Environmental Impact Assessment (EIA). Part of the EIA will involve the assessment of potential impacts on intertidal ecology, related to the proposed onshore cable route options at Peterhead. To inform the EIA and to evaluate the potential for impacts on intertidal ecology, SWL has appointed Xodus Group to undertake a marine intertidal Phase 1 biotope mapping survey. The aim of the survey was to characterise and map baseline ecological conditions within the survey area. At the time of the survey three potential locations for bringing the export cable ashore (cable landfall) were under consideration within the intertidal survey area: one located across the mouth of the River Ugie in the north; one at the sandy bay at The Ive in the middle of the survey area; and another to the south of the survey area adjacent to the harbour sea defences.
Series2013, MMT, Hywind Offshore Wind Farm, Geophysical Survey
MMT was contracted by Statoil to undertake a geophysical and benthic survey for the Hywind Offshore Windfarm – Seabed and sub-seabed mapping of development site and export cable corridor. The scope of work included seabed and sub-seabed survey of the Hywind Offshore Windfarm development site and the export cable corridor. The main aims with the survey were to: - Acquire and interpret high quality seabed and sub-seabed data for project planning and execution, including shallow geology, bathymetry, seabed sediment distribution and detection of seabed features and seabed obstructions. - Detect possible occurrence of benthic habitats and species of known conservation importance. - Improve the geological understanding of the shallow stratigraphy and sediment properties in the turbine site and export corridor to facilitate the planning and execution of turbine foundation installation and cable routing, installation and protection. - Detection of three cables. The Hywind Offshore Windfarm site is located on the east coast of Scotland at the Buchan Deep site, approximately 25 km east of Peterhead (Figure 1). The development will consist of five floating wind turbines, anchored to the seafloor each with connection to an export cable. The survey area is divided in two main parts; the turbine site area with accompanied construction and anchoring areas and the export cable corridor. The development area is approximately 60 square km but is limited by the Forties pipeline exclusion zone (2000 m wide) running in a NE-SW direction (Figure 1). The export cable corridor is 25 to 30 km long and 500 m wide, with a planned landfall in the Peterhead area. The turbine site area has water depths in the range of 110 to130 m.
Series2013, Xodus Group, Hywind Offshore Wind Farm, Landfall Site Walkover - Geotechnical Evaluation
Statoil are planning to develop an offshore wind farm Pilot Park approximately 25 km to the east of Peterhead on the Aberdeenshire coast covering an area of approximately 60 km2. The Pilot Park will be located either to the north or south of the BP Forties C to Cruden Bay Pipeline, which runs through an Exclusivity Area associated with the development. The Pilot Park will consist of 5 turbines that will be up to 6 MW in size (30 MW maximum). The turbines will have a maximum height of 101m with a rotor diameter of up to 154 m maximum and a draft of 80 m. The Pilot Park will export energy via a power cable to shore at a proposed landfall location. At present 3 No.landfall options are being considered to the north of Peterhead Harbour, as shown in Figure 1. The proposed offshore export cable route options are presented in Figure 2 with 2 No. possible substation locations marked in red. The scope of this series is to present the findings from a brief engineering geological site walkover of each proposed landfall site to understand the geomorphological and technical constraints each site offers. The walkover was performed on 16th July 2013 between 11:00 – 13:00 during low tide.
Series2013, Xodus Group, Hywind Offshore Wind Farm, Marine Noise Desk Study
The report in this series provides a high level overview of the potential impacts due to underwater noise from Hywind on the surrounding environment. In particular, the report reviews the underwater noise measurements and analysis previously undertaken by Statoil on the Hywind I demonstrator installed offshore Norway, to assess operational noise from the turbines. The report also makes recommendations for the types of impacts identified should be addressed in the EIA in terms of marine noise.
Series2013-2014, Caloo Ecological Services, NRP, Hywind Offshore Wind Farm, ESAS Seabird and Marine Mammal Surveys
The Technical Report within this series is concerned with the environmental studies undertaken to inform the EIA and HRA of seabirds and marine mammals for the proposed Hywind Scotland Pilot Park Project, a demonstration floating offshore windfarm being progressed by Hywind Scotland Limited (HSL). The report presents results for the one-year programme of boat-based baseline European Seabirds at Sea (ESAS) surveys together with relevant context information on regularly occurring species. The Survey Area covers 170.5 km2 and comprises the original Exclusivity Area buffered to 3 km. This area is covered by 23 parallel transects spaced 0.75 km apart and with a total length of 228 km. Surveys of all 23 transects took two days to complete, with alternate transects surveyed on one day and the other set of alternates on the other day. This regime meant that on each survey day the whole Survey Area was covered. The surveys were conducted following the ESAS method. This involves a team of two accredited surveyors on board a survey vessel collecting data on all birds and marine mammals seen in a 300 m wider survey corridor in a format that is suitable for distance sampling analysis. Two survey days of effort (i.e. surveying each transect once) were scheduled at monthly intervals from June 2013 to May 2014. A total of 20 surveys (days) were undertaken over the year. Eight additional surveys were undertaken between July and September 2014 using the same survey design and methods. These surveys are reported separately (Caloo 2014c (Annex 3 to Technical Report) however the results are used as additional evidence to characterise the ornithology of the Survey Area. Statistical analyses of the seabird data were undertaken by Caloo Ecological Services. These analyses are provided as Annexes to this Technical Report: Annex 1 - Caloo 2014a. Distance sampling analyses of year 1 ESAS survey results for the Hywind Scotland Pilot Park; Annex 2 - Caloo 2014b. Collision risk modelling with respect to seabirds for the Hywind Scotland Pilot Park; Annex 3 - Caloo 2014c. Distance sampling analyses of additional (July – September 2014) ESAS survey results for the Hywind Scotland Pilot Park. In addition to the analyses presented in the above reports, Marine Scotland, SNH and JNCC requested some alternative analyses of the survey data based on the breeding seasons specified by SNH / JNCC. These analyses have been reported in the following standalone report: Caloo 2014d. Alternative density, abundance and collision risk mortality estimates based upon breeding seasons as specified by SNH/JNCC for seabirds using the waters of the Buchan Deep off the Aberdeenshire coast for the period June 2013 to May 2014 in support of the Hywind Scotland Pilot Park project. Substantial detail on data analysis and results is provided in these four reports, the essence of which is presented throughout the EIA. Where relevant, cross-references to tables have been used to aid the reader’s interpretation of the assessment and underlying analytical output.