Summary
In August 2013 EGS International were commissioned to carry out bathymetric surveys of the London Array Export cable routes. The Bathymetric surveys were to cover the 4 export cables corridor as laid and with a buffer of 25m either side of the outermost cable. The vessel mobilisation was carried out in Ramsgate between 27th and 30th August 2013. T...