2011-2012, Brown and May Marine, Lynn and Inner Dowsing, Year 3 Potting Survey

2011-2012, Brown and May Marine, Lynn and Inner Dowsing, Year 3 Potting Survey

Summary

As part of the environmental monitoring programme outlined within FEPA licences 31792/10/1 and 31814/10/2 for the Lynn and Inner Dowsing (LID) wind farms respectively, both valid from the 10th October 2010 until the 31st October 2013, Brown & May Marine Ltd. was commissioned by GLID TopCo Limited to undertake post-construction fisheries surveys within the LID wind farms. This report details the findings of the 19th to 24th potting survey undertaken in the area relevant to the operational Lynn & Inner Dowsing offshore wind farms. The survey is the Year 3 post construction survey which span across 2011 and 2012.
Categories
Epifauna and Fish
Development
Lynn and Inner Dowsing
Industry
Wind
Phase
Post-construction
Organisation
Brown & May Marine Ltd
Available in this series
2 Datasets, 2 Reports

Data & downloads

Datasets

Data Highlights