2010, LDA Design, Triton Knoll, 8MW Scheme Project
Summary
Data & downloads
Reports
Related Pages
Series2020, Seiche, Triton Knoll, Analysis of Underwater Noise and Source Level Estimation
An underwater acoustic survey was carried out during the installation of the first four foundations V11, V12, U10, and T09 between 17th January 2020 and 26th February 2020. This survey was performed to record the noise levels emitted during installation. The levels were measured at different distances from the piles and results were compared to the outputs of a prior modelling outcome. The report in this series presents the results and subsequent analysis of the underwater noise data recorded in this survey. The data was analysed using signal processing and acoustic propagation modelling for the survey region and Source Levels based on recorded data were reported. The underwater noise levels were recorded using two calibrated Acoustic Recording Units (ARUs) deployed at 500 m and 750 m from the foundations along pre-defined transects. In addition to ARUs, a Vertical Sound Profiling (VSP) system with a hydrophone was deployed from the starboard side of the noise monitoring vessel at distances between 4 km and 12 km. The recorded data was processed using peak detection algorithms to identify individual strike data and these are matched with relevant hammer strikes. The matched strikes were post-processed into different frequency bands and their Received noise Levels (RL) were calculated.
Series2018-2019, Fugro, Triton Knoll Offshore Wind Farm, Geophysical, UXO and Environmental Surveys
Triton Knoll Offshore Wind Farm Ltd. contracted Fugro to perform geophysical, UXO and environmental surveys in the Triton Knoll Offshore Wind Farm site, approximately 18 NM from the Lincolnshire coast and 25 NM from the Norfolk coast. The survey operations were performed onboard the Fugro Mercator during the survey period 8 July 2018 to 6 January 2019 and onboard Fugro Galaxy during survey period 17 December 2018 and 20 December 2018 . Survey operations were also performed onboard the M.V. Fugro Frontier during the survey period 23 July to 22 October 2018 and the nearshore survey operations onboard the Fugro Seeker during the survey period 25 June to 17 August 2018.
Series2016, Fugro Geoconsulting, Triton Knoll, Site Investigation
Triton Knoll Offshore Wind Farm Limited (TKOWFL) requested Fugro to perform a geotechnical investigation at the Triton Knoll Offshore Wind Farm site to obtain information to assist in the design and installation of wind turbine generators, electrical substations and the associated cable routes. The geotechnical fieldwork was performed from the following vessels: i. MV GloMar Vantage from 16 June to 27 July 2016; ii. MV Gargano from 28 June to 22 July 2016; iii. JIF Challenger from 2 July to 24 July 2016. The field operations and preliminary results reports (Fugro, 2016a, b and c) present full details of the fieldwork performed from each vessel. The geophysical fieldwork was performed from the following vessels: i. Fugro Seeker – base scope from 23 June to 6 July 2016; ii. Fugro Seeker – additional survey from 18 July to 20 July 2016; iii. GeoFocus from 1 July to 14 July 2016. Previous geotechnical site investigations were performed at the Triton Knoll site from the jack-up barge Excalibur from 14 June to 10 July 2009 and from the jack-up barge Sound Prospector from 9 August to 9 October 2015. Results of the previous investigations can be found in the corresponding final laboratory and in situ data reports (Fugro, 2009 and 2016d). Reporting for the project has been sub-divided into 5 volumes for field operations and preliminary results. Additionally reports have been further sub-divided into 3 volumes for measured and derived geotechnical parameters and final results.
2015-2016, Gardline, Triton Knoll, Metocean Survey
Gardline Environmental was commissioned by Triton Knoll Offshore Wind Farm Ltd to undertake a metocean survey at the Triton Knoll Offshore Wind Farm site. Three sites were selected at which oceanographic instrumentation were deployed to acquire wave spectra, current profiles and water levels. Initially, two waveriders and a seabed mounted AWAC and databuoy, were deployed at the three locations across the site. In addition, marker buoys, two per site, were deployed alongside the instrumented moorings. In the weeks following deployment, both waveriders were struck by 3 rd party vessels and set adrift. Telemetry from the data buoy also ceased during the same time period. Further investigation on site also revealed that none of the marker buoys remained on site. In light of the impact of 3 rd party interference with the moorings Triton Knoll and Gardline agreed a different approach to acquisition whereby two of the three sites would contain sub-surface AWACs, without surface signatures, with one site continuing with a deployed waverider. While a full data record was acquired at the Met Buoy 1 site, the instrumentation at Met Buoy 3 again suffered 3 rd party interference which resulted in the frame being turned upside-down mid-way through the deployment. While the data acquired is deemed to be of good quality, the quantity of data collected during the first deployments between October 2015 and January 2016 makes it difficult to determine whether the data are representative of the site during this time period. The second deployment period between January 2016 and April 2016 saw improved deployment durations containing good quality data. Sites Met Buoy 1 and Met Buoy 3 contained data that was deemed representative of the site.
Series2015, Gardline Geosurvey Limited, Triton Knoll, Geophysical Survey
Gardline Geosurvey Limited carried out a geophysical survey for Triton Knoll Offshore Wind Farm Limited (TKOWFL) situated 33km off the coast of Grimsby covering an area of 143km². The proposed survey consisted of an Unexploded Ordnance (UXO) survey over 18 proposed borehole locations, an Ultra-High Resolution Seismic (UHRS) survey and a sand wave migration study over two areas within the Triton Knoll Offshore Wind Farm (TKOWF) site. The data acquisition programme commenced on the 12-Jul-2015 and was carried out by two vessels; the M.V. Confidante and the M.V. Ivero. The M.V. Confidante undertook a UXO investigation survey covering 18 proposed borehole locations in preparation for a geotechnical investigation. The M.V. Ivero undertook a UHRS survey covering the main Triton Knoll Offshore Wind Farm area as well as the sand wave mapping investigation. Reporting for the project has been sub-divided into four volumes.
Series2015, PMSL, Triton Knoll, Report on Guard Vessel duties undertaken by the Jubilee Pride
In May 2015, Triton Knoll Offshore Wind Farm Limited contracted Precision Marine Survey Limited (PMSL) to supply a suitable guard vessel to assist the geophysical and geotechnical investigations within the Triton Knoll Offshore Wind Farm (TKOWF) development envelope. The deployment of a guard vessel during the 2015 site investigations (SI’s) was prompted by significant concern raised by local static gear fishermen active in the TKOWF site. These concerns were first raised by Bridlington based fishermen during the consultation of 2013, and which identified that there was a high risk of large nomadic scalloping vessels from Scotland and the English south coast (Shoreham) entering the TKOWF site. The key issue was that once static gears had been removed to facilitate the SI’s, scallop vessels would enter the site and tow away large quantities of static fishing gear and extensively damage the traditional fishing grounds during the scallop dredging activity. PMSL initiated a review of suitable, local vessels to undertake the guard duties and confirmed on the 1st June 2014, that the Grimsby registered Jubilee Pride, owned and operated by a local company Jubilee Fishing Co Ltd, was both suitable and available.
Series2013, Gardline Geosurvey, Triton Knoll, Seismic Hazard Survey
Gardline Geosurvey Ltd carried out an HR seismic hazard survey for RWE Npower Renewables at the Triton Knoll Offshore Wind farm to investigate the shallow soils conditions using single beam and multi-beam echo sounders, sub-bottom profiler, sparker as a source for Ultra High Resolution digital seismic (UHR 2D), 3m vibrocores, 5m miniature cone penetration tests (MCPT) and drop camera visualization.
Series2012, Osiris Projects, Triton Knoll, Export Cable Route Survey
Osiris Projects were commissioned in April 2012 by RWE npower renewables and Senergy Survey and GeoEngineering to carry out a geophysical and geotechnical cable route survey along the proposed Triton Knoll Export cable route. The proposed Triton Knoll Offshore Wind Farm is located in the Greater Wash Strategic Environmental Assessment (SEA) area, approximately 18nm from the Lincolnshire coast and 25nm from the Norfolk coast.
Series2012, Osiris Projects, Triton Knoll, Export Cable Geophysical Survey
Geophysical survey carried out at the Triton Knoll Offshore Wind Farm site by Osiris in 2012. Data collected includes multibeam bathymetry (XYZ), magnetometer (TEXT), sub-bottom profiler (pinger; SGY) and side scan sonar (XTF and mosaics).
Series2011, Spaven Consulting, Triton Knoll Offshore Wind Farm, Investigation of Potential Impacts on Helicopter Access to Offshore Gas Platforms
This report assesses the potential impact of the Triton Knoll offshore wind farm on helicopter operations to and from adjacent gas platofrms in the Southern North Sea. The Triton Knoll Wind Farm will consist of between 150 and 333 wind turbines with a tip height of up to 220m, 33km off the Lincolnshire coast. Seven offshore installations have the potential to be affected by the Triton Knoll Wind Farm - the Amethyst A1D, A2D, B1D and C1D; the Pickerill A and B; and the Guinevere. Potential effects on helicopter operations to platforms in the vicinity of Triton Knoll have been assessed using methodology developed in support of the Gwynt y Mor Offshore Wind Farm in Liverpool Bay and adapted in response to consultations with the helicopter operators.
Series2010, Subacoustech, Triton Knoll, Underwater Noise Impact Modelling
Subacoustech Environmental has undertaken a study to model the potential impact underwater noise generated by piling operations during the construction of the Triton Knoll Offshore Wind Farm (TKOWF) could have on local populations of fish (specifically, herring, sole and lemon sole) and marine mammals (specifically, harbour porpoise and harbour and grey seals). The levels of underwater noise from the installation of 7.0 m and 8.5 m diameter piles at two representative piling locations have been estimated using a proprietary underwater sound propagation model (INSPIRE v18) that enables the level of noise from the piling and its behaviour with range to be estimated for varying tidal conditions, water depths and piling locations. The model is based on, and validated against, an existing database of measurements of piling noise.
Series2010, Eagle Lyon Pope, Triton Knoll Offshore Wind Farm, Drifting Ships - Risk Analysis
NPower Renewables has been granted an agreement for lease of the Triton Knoll Wind Farm in the Great Wash Strategic Environmental Assessment Area. As part of their EIA, NPower Renewables instructed Eagle Lyon Pope (ELP) to analyse the drifting behavior of vessels in the vicinity of Triton Knoll. The frequency of a vessel drifting and crossing the boundary of the planned wind farm was determined using OCTAVIA, ELP‟s proprietary software which enables the drift behaviour of vessels such as tankers, containers, roros and bulkers to be modelled. The analyses were based on the annual vessel movements on four main shipping routes in the vicinity of the wind farm area. The study was extended to investigate the probability of a fishing vessel or a dredging vessel, that has lost engine power when working in the immediate vicinity of Triton Knoll, drifting into the wind farm area. The study was undertaken for four fishing vessel and four dredging vessel start locations, each of which was defined by RWE NPower.