2005-2007, Fugro, Wave Hub (Hayle), Wave and Current Measurements
Summary
Data & downloads
Datasets
Related Pages
Series2017, Rovco Limited, Wave Hub (Hayle), Installed Asset ROV and Bathymetry Survey
Rovco Limited was commissioned by Wave Hub Limited, under the project management of Offshore Marine Management Ltd (OMM), to conduct an ROV inspection and Multibeam Echo Sounder (MBES) campaign of the Wave Hub offshore electrical infrastructure including: - 33KV Export Cable - Four Cable Tails The report in this series contains an overview of the equipment, vessels and processes used to collect data during operations as well as providing evidence of the current state of the export cable and cable tail extensions.
Series2016, Insight Marine Projects, Wave Hub (Hayle), Cable Tail Installation As-Built Survey
Insight Marine Projects Ltd were contracted to supply construction support services to James Fisher Marine Services Ltd during the cable tail extensions project at the WaveHub wave energy test site, Cornwall, UK. Installation of the cable extensions was undertaken onboard OSCV ‘Aker Wayfarer’. An ‘As-Built’ visual (ROV) and multibeam (MBES) survey was conducted immediately after the installation work to verify the position of the cables as well as cable stabilisation and freespan rectification measures.
Series2015-2016, Fugro EMU, Wave Hub (Hayle), Wave Monitoring Buoy
On 22 May 2015 Fugro Emu deployed a Waverider Buoy at the Wave Hub offshore test site for up to five years of data collection. The buoy was deployed at (WGS84): 50° 20.833'N 005° 36.853'W The buoy and works relating will generally be confined within the charted Wave Hub Safety Zone which mariners should avoid as usual. The data from the buoy is publicly available for the benefit of all mariners operating in the area: http://www.wavehub.co.uk/wave-hub-site/live-wave-data. This series contains the Wave Monitoring Buoy Annual Reports which provide an assessment of the wave conditions on site from the 01 June 2015 to 31 December 2017 and also the associated data.
Series2015, MMT, Wave Hub (Hayle), Cable Protection Area Rock Bag Installation Survey
Mojo Maritime installed cable protection on the Wave Hub 33KV export cable off the coast of North Cornwall. Stril Explorer was used as platform to accurately place rock filled fibre mesh bags, control their position with ROV and perform a post installation hull-mounted MBES survey. The ROV fix positions were monitored and approved on board the vessel by the client representative. The post rock bag installation survey provided good quality high resolution bathymetry over the cable protection area and rock bag installation. To cover the surveyed area, a site chart with horizontal scale of 1:250 has been produced. The site chart presents the bathymetry with colour coded background representing depth, together with the fix positions logged with the ROV.
Series2014, Insight Marine Projects, Wave Hub (Hayle), Bathymetry Cable Route Survey
The primary objectives of the 2014 survey were to perform bathymetric survey works to assess any significant changes to the Subsea Power Cable (SPC) rock dumping and mattress stabilisation measures which were installed in 2011. The scope of work was a Multibeam Bathymetric Survey: High resolution bathymetry using multibeam techniques to acquire data between KP 1.900 and the Hub at KP 25.150, including 4 x cable tails radiating from the hub itself. Survey standards to meet those stipulated by IHO Order 1A for Hydrographic Surveys.
Series2013, Coastline Surveys, Wave Hub (Hayle), Geotechnical Site Investigation
Coastline Surveys Ltd (CSL) was commissioned by Wavehub Limited (WHL) to undertake a marine geotechnical site investigation for the Wavehub Asset area. The aim was to obtain information on the geotechnical characteristics of the sediment at selected locations within the development area. A Vibrocore (VC) survey campaign involving 5 No. x 6m VC at locations supplied by Wavehub Ltd has been completed by CSL onboard Coastline’s dedicated survey vessel “MV FlatHolm” (Plate 1). The vibrocore survey was carried out on July 5th 2013 using the CSL C-CoreHP High Penetration Corer.
Series2013, Coastline Surveys, Wave Hub (Hayle), Test Centre and Cable Route Bathymetry Survey
The Wave Hub Ltd seabed survey was carried out by the Coastline Surveys Ltd dedicated survey vessel MV FlatHolm between 4th July and 10th August 2013. The survey was split into three phases with a combination of Multibeam Echo Sounder and Side Scan Sonar techniques used in phase 2 to complete the bathymetry survey which is covered in this report. A high quality set of inspection data has been collected. Further analysis of this data set compared to the previously acquired baseline data set will give a guide to the stability and changes observed in the seabed assets environment.
Series2013, Osiris, Wave Hub (Hayle), Test Centre and Cable Route Geophysical Survey
Osiris Projects were commissioned in February 2013 by Wave Hub Limited to carry out geophysical surveys of the Wave Hub ‘Offshore Deployment Area’. The site was divided into four ‘berths’, with an export cable route to the landfall point in Hayle. The main focus on the survey was the northern section, Berth 4, which was of interest to a Wave Hub client. The remaining berths and cable route were to be surveyed as much as possible until budget close down at the end of March 2013. Due to the impact of adverse weather, it was not possible to start survey operations on the cable route within that timeframe. It was also not possible to complete all of the cross-lines for Berths 1 - 3 and some small areas also remained unsurveyed. The main objectives of the surveys were as follows: To provide accurate bathymetry. To identify any seabed obstructions. To provide resolution of the upper seabed sedimentary units, as well as to penetrate the underlying lithological units down to a depth of 60m below seabed. In 2015, Osiris Projects were commissioned by Wave Hub Limited to provide a dataset and interpretation overview for the complete development area. Bathymetric data from previous surveys were provided by Wave Hub Limited for incorporation into the dataset, in order to cover the small areas left unsurveyed in 2013.
Series2011, EMU, Wave Hub (Hayle), Benthic Ecology Monitoring Survey
EMU Limited (EMU) were commissioned by the South West Regional Development Agency (SWRDA), under management by Halcrow Group Ltd., to supervise a baseline benthic ecology survey at the Wave Hub deployment site and associated sub-sea export cable. The survey was undertaken to meet Wave Hub’s preconstruction obligations under the Food & Environmental Protection Act (FEPA) (1985), to acquire information as part of a wider survey campaign, and to make suggestions to establish a programme of environmental monitoring. An interim survey report was presented in June 2010 outlining field data acquisition methods used during the Wave Hub survey together with preliminary field observations derived from grab sampling and seabed video. It was recommended that a post construction survey be undertaken at a 1 year interval, at a similar time of year to that of the previous survey, undertaken in 2010. This should have resulted in a survey being undertaken between June and August 2011 but due to a lack of suitable weather windows, the survey was finally undertaken in November 2011. However the survey was undertaken before any major changes in sea temperature had occurred and as such, no particular effects of the survey delay on data acquisition or quality of data was noted.
Series2011, EMU, Wave Hub (Hayle), Noise Survey
This report has been prepared by Subacoustech Environmental Ltd for EMU Limited. It describes the baseline conditions found at the site for the installation of a wave energy facility, approximately 15 km off the north coast of Cornwall. A number of background underwater noise measurements were taken at five locations for a minimum duration of 15 minutes and repeated after a delay of over 1 hour.
Series2011, EMU, Wave Hub (Hayle), Test Centre Cable Route Baseline Hydrographic Survey
EMU Limited was commissioned by Halcrow Group Limited to conduct a baseline hydrographic survey. The survey was undertaken between the 27th September and the 29th September 2011 onboard Nab Cat II, an 11 m survey vessel operating out of St Ives. The purpose of the survey was to provide a baseline for future post‐construction monitoring surveys covering the Wave Hub site, the sub‐sea power cable (SPC) route and an area covering the wreck “Helene”. The bathymetric survey accurately charted depths within the three survey areas.
Series2010, EMU, Wave Hub (Hayle), Benthic Ecology Survey
Emu Ltd. were commissioned by the South West Regional Development Agency (SWRDA), under management by Halcrow Group Ltd., to supervise a baseline benthic ecology survey at the Wave Hub deployment site and associated sub-sea export cable. The survey was undertaken to meet Wave Hub’s pre-construction obligations under the Food & Environmental Protection Act (FEPA) (1985), to acquire information as part of a wider survey campaign, and to make suggestions to establish a programme of environmental monitoring. An interim survey report was presented in June 2010 outlining field data acquisition methods used during the Wave Hub survey together with preliminary field observations derived from grab sampling and seabed video. The purpose of the survey was to build on previous data acquired and reported on by Fugro Survey Ltd, undertaken in October 2005, and a repeat survey with revisions by Precision Marine Survey Ltd in May 2006. The initial Fugro survey was a more extensive analysis of the area than either of the subsequent surveys, incorporating 30 grab stations for faunal analysis, Particle Size Distribution (PSD), Total Organic Carbon Analysis (TOC), 18 video transects analysed for the application of biotope codes and 20 beam trawls.