2010-2012, Fugro, Greater Gabbard, Interconnector and Inter Array Cable Depth of Burial Survey

2010-2012, Fugro, Greater Gabbard, Interconnector and Inter Array Cable Depth of Burial Survey

Summary

Greater Gabbard Offshore Winds Ltd have recently completed the construction of a wind farm approximately 14mi east of Suffolk coast. The offshore wind farm consists of 152 Wind Turbine Generators (WTGs) with a gross nameplate capacity of approximately 504MW. The project is now fully operational and the construction was completed in September 2012. GGOWL signed up CT Offshore to conduct survey of the inter array cables. This report provides a summary of the export and interconnector cable depth's of burial and alignment.
Categories
Geophysical
Development
Greater Gabbard
Industry
Wind
Phase
Post-construction
Organisation
Fugro
Available in this series
1 Dataset, 1 Report

Data & downloads

Datasets