2011, Subacoustech, Gunfleet Sands 1 and 2, Subsea Operational Noise Assessment

2011, Subacoustech, Gunfleet Sands 1 and 2, Subsea Operational Noise Assessment

Summary

This project has been prepared by Subacoustech Environmental Ltd for DONG Energy Power (UK) Ltd. It describes a series of high quality underwater acoustic measurements undertaken in and around the operational Gunfleet Sands Offshore Wind Farm site. on the 17th, 18th and 19th April 2011. The purpose of the measurement programme was to characterise any increase in the ambient subsea noise due to the presence of the operational wind farm, and to assess the range over which any increase in noise occurred.
Categories
Noise
Development
Gunfleet Sands 1 and 2
Industry
Wind
Phase
Post-construction
Organisation
Subacoustech
Available in this series
1 Report

Data & downloads

Reports