2008, Osiris Projects, Barrow Offshore Wind Farm, Post-Construction Cable Route Inspection and Scour Monitoring Survey

2008, Osiris Projects, Barrow Offshore Wind Farm, Post-Construction Cable Route Inspection and Scour Monitoring Survey

Topic categories:

Geophysical

Last series update:

May 2021

MEDIN approved

Industry:

Wind

Collection date:

May 2008 - Nov 2008

Development:

Barrow

Publication date:

May 2021

Round:

1

Organisation:

Osiris Projects

Phase:

Post-construction

Description

On the instructions of Barrow Offshore Wind Limited, Osiris Projects were
commissioned to undertake an inspection survey covering the Barrow Offshore Wind
Farm export cable route, in conjunction with scour monitoring surveys at a series of
selected turbine locations within the main development area. Data acquisition took
place using the survey vessel MV ‘Barinthus’, during the period 10th to 15th May 2008 and on the MV 'So Fyne', during the period 15th to 30th November.
High-resolution side scan sonar, swath multi-beam and single beam bathymetry data
were acquired along a number of parallel survey lines, which were generally run at 25m
centres, in order to accurately map the seabed along the cable route.
The package contains a final report from the May surveys and a draft report from the November survey.