Ørsted Power contracted EGS international Ltd (EGSi) to undertake a bathymetric survey at Burbo Bank Extension Wind Farm (BBW02) in the Irish Sea. Data was acquired in September 2019. Operations were undertaken using a hull mounted dual head Kongsberg 2040C. The surveys were conducted onboard the EGS owned coastal survey vessel ‘The Watchful’, which operated on a 12hr basis from Liverpool marina. Vessel mobilisation, calibrations and verifications began between 22nd and 23rd August 2019 whilst the vessel was in Liverpool and were then completed offshore 24th August. All survey operations were completed on 13th September 2019.