2015, Cathie Associates, Burbo Bank Extension Offshore Wind Farm, Cable Burial Risk Assessment

2015, Cathie Associates, Burbo Bank Extension Offshore Wind Farm, Cable Burial Risk Assessment

Topic categories:

Geotechnical

Last series update:

May 2021

MEDIN approved

Industry:

Wind

Collection date:

Aug 2015 - Aug 2015

Development:

Burbo Bank Extension

Publication date:

May 2021

Round:

1&2 Extensions

Organisation:

Cathie Associates

Phase:

Pre-construction

Description

Cathie Associates have been commissioned by DONG Energy to perform a Burial Risk Assessment (BRA) for the inter-array cables and the export cable.
The purpose of the BRA is to determine the minimum burial depths required to achieve the protection requirements of the project with regard to natural and anthropogenic hazards. In addition, the study wi...